Individual application to install charging pile

2020-07-27
Individuals applying for the installation of charging piles need to apply to the power supply bureau. An electric vehicle can currently apply for 1-2 charging piles. If users without fixed parking spaces need to coordinate the installation location with the community property office in advance, the installation of charging piles will not apply To charge fees, users need to fill in the "Registration Form for the Construction of Supporting Electric Vehicle Charging Pile" and the owner's ID card and vehicle driving permit.
Hongjiali
The process of individual application for installation of charging pile is as follows:

1. When an individual applies for the installation of a charging pile, he must provide the identity information of the owner of the charging pile to the power supply department.
2. To install in the community, the opinions of the owners need to be collected and approved by most owners.
3. The community property shall apply to the neighborhood committee, street office and other departments and obtain approval from the department.
4. Fixed parking spaces can only be installed with the permission of the property. In order to avoid disputes, try to provide and discuss with the property about wiring problems.
5. Charging piles need to be installed in public areas, and a written approval certificate must be issued through the local street office/community.
6. Submit an application to the power supply department, and after it is approved, it will be required to guide the construction of power supply devices and charging devices.
7. After completion, please send someone from the power supply and fire control departments to check and accept.

Individuals applying for the installation of charging piles must first meet two conditions: they must have their own dedicated parking spaces and have sufficient power supply conditions, and then go to the property and the local power supply bureau to apply for the installation of charging piles. If they encounter interference, they will complain to the community leader. , Basically it can be done.

Shenzhen Hongjiali New Energy Co., Ltd.
Business Type:Manufacturer , Service
Product Range:Battery Charger , Battery Charger
Products/Service:ev charger , dc ev charger , car charger , evse charger , charging pile , Charger cabinet
Certificate:ISO10012 , ISO14001 , ISO9001 , GB , CCC , CE , EMC , RoHS , TUV , UL , OHSAS18001
Company Address:West 2nd Floor, Building 68, Changxing Science and Technology Industrial Park, Changzhen Community, Yutang Street, Guangming New District, Shenzhen, Guangdong, China

Previous: Shared charging pile market capacity

Next: Can you make money as a car charging station

Related Products List

Home

Phone

Skype

Inquiry